Version 1.2, May 2018 Application Note – Alternate Current Transformer Selection, North America Version history Version 1.2, April 2018 – product name change from "SolarEdge Electricity Meter" to "Energy Meter" Version 1.1, January 2018 – clarified CT compatibility requirements and added CT options Version 1, October 2017 – initial version Introduction The Energy Meter (refer…
ON/OFF/P Switch Replacement in Energy Hub Inverters Kit Contents ON/OFF/P switch with cables Mounting nut Gasket Plastic tie Required Tools 4mm Allen key Knife Pliers Removing the Inverter and Connection Unit Covers 1. Turn off the ON/OFF/P switch. Wait 5 minutes. 2. Turn off the DC switch on the Connection Unit. 3. Turn off AC to the inverter on the main distribution panel. 4. Release the Allen…